Project overview

An Atlanta based engineering firm asked Fibrelite to solve a problem for the CDC location in Atlanta GA. The facility has a new diesel fueling fuelling facility where vehicles are fueled. fuelled. They wanted to have easy access to their overspill vault set across the street from the loading facility.

Solution

Fibrelite’s heavy duty trench covers to be installed directly on a newly made concrete trench crossing the street.

Pre-install location for the Fibrelite covers
Pre-install location for the Fibrelite covers
Completed project with Fibrelite's heavy duty covers installed
Completed project with Fibrelite's heavy duty covers installed

Heavy duty trench on the street allows street traffic to drive over and offers a low weight solution to the Center Centre of Disease Control’s complex needs. Fibrelite’s range of heavy duty covers was designed for such an application. The main requirement for access the containment vault were met.

Fibrelite covers offer a clean lightweight alternative to heavy and iron concrete covers
Fibrelite covers offer a clean lightweight alternative to heavy and iron concrete covers

Author:

Picture of Jim Goodman

Jim Goodman

Author Bio
Share this story on
LinkedIn

Featured products:

Back to
case studies

D400
Trench Covers

FL7
Lifting Handles

Download
PDF

Contact us to discuss your project