On this flood defence site, the previously installed steel access plates which were used to securely stow away flood defence doors had deformed which, together with their weight...
Read MoreOn this flood defence site, the previously installed steel access plates which were used to securely stow away flood defence doors had deformed which, together with their weight...
Read MoreApproximately 625 metres of custom designed and manufactured Fibrelite GRP trench covers and frames were specified for this project at one of the UK’s largest power stations...
Read MoreWith a fleet of 200 buses stationed, serviced, and refuelled at MPK Poznan depot in Poland, the Poznan Municipal Transport Company required an easy access covering solution…
In order to utilize the power generated by nearly 30,000 solar panels installed on 150 acres of unused farmland in southeastern Connecticut, a regional utility needed to install…
In this project we were approached by an OEM who provides Onshore Power Supply (OPS) systems, to quote for this large leisure cruise terminal upgrade project.
Under the EU’s renewable energy plan (still in place post-Brexit) the UK set targets to meet 15% of their energy needs from renewable sources by 2020, including generating 30% of electricity from wind, solar and other low carbon sources (The Guardian, 2016). Wales selected 7 SSAs (Strategic Search Areas) which were chosen for good wind speeds and lack of statutory designations. One of these was selected as a site for Garreg Lwyd large scale wind farm, which will be capable of providing sufficient renewable electricity to meet the average needs of more than 26,000 homes.
The project consists of 17 turbines, a control building and a substation to supply power to the grid at the correct voltage and amperage. Substations require large amounts of cabling and other utilities set below the ground while being easily accessible.
When considering materials and products to use when building this power station of the future, they specified future materials and products that will endure into it.
At the substation, there are two long precast concrete trenches: one 19 meters metres long with a span of 765 mm, the other 25 meters metres long with a span of 1250 mm. The trenches are set flush into the ground, with an edging created using upright concrete slabs. The trenches required a covering solution that could be easily manually removed for maintenance and monitoring while performing at D400 load rating (40 ton). tonne). The Substation specified a FRP GRP composite solution to meet the required specifications. Covers also needed to provide a safe walking surface for operators, whatever the weather conditions.
Stanton Bonna, the precast trench manufacturer partnered with Fibrelite to create a series of custom FRP GRP trench covers to fit onto their precast concrete trenches.
Stanton Bonna, the precast trench manufacturer partnered with Fibrelite to create a series of custom FRP GRP trench covers to fit onto their precast concrete trenches.
Fibrelite designed and manufactured a series of custom FRP GRP trench covers to fit onto the Stanton Bonna precast concrete trenches. Covers are ‘stepped’ to reduce unit weight and increase the load rating capability. The D400 load rated 1250 mm wide covers can be safely manually removed by two operators without risk of injury. The equivalent size concrete panel would have weighed approx. 400Kg. Independent wet and dry tests carried out by Devon CC Materials Laboratory showed that Fibrelite manhole and trench covers – even when wet – have anti-slip/skid properties far exceeding health and safety advisory limits.
Fibrelite covers are a fit-and-forget solution: no maintenance is required, and the composite material has an inherent resistance to corrosion. Structural performance is guaranteed for years to come, with all covers independently tested to BS EN124 criteria.
Lifting and manual handling issues are eliminated. All Fibrelite FRP GRP trench covers are safely removable by two operators, even at D400 (or F900!). This means increased efficiency on site when performing essential maintenance while preventing the risk of injury or need for specialized specialised heavy lifting equipment.
Author: