On this flood defence site, the previously installed steel access plates which were used to securely stow away flood defence doors had deformed which, together with their weight...
Read MoreOn this flood defence site, the previously installed steel access plates which were used to securely stow away flood defence doors had deformed which, together with their weight...
Read Moreerpecnews Editor Nick Needs recently interviewed our Sales Director, OPW Retail Fuelling EMEA, Denis Pokrovsky, to discuss our growth into new markets. "The Middle East and Africa have slightly different...
Read MoreApproximately 625 metres of custom designed and manufactured Fibrelite GRP trench covers and frames were specified for this project at one of the UK’s largest power stations…
With a fleet of 200 buses stationed, serviced, and refuelled at MPK Poznan depot in Poland, the Poznan Municipal Transport Company required an easy access covering solution…
In order to utilize the power generated by nearly 30,000 solar panels installed on 150 acres of unused farmland in southeastern Connecticut, a regional utility needed to install…
Fibrelite was approached by RJ Utilities Ltd to provide a safe, long-term replacement for old, failing concrete trench covers which covered essential underground utilities. For this project, ease of access, customisability and safety were of the highest importance.
Previously, heavy concrete trench covers had been fitted over below ground utilities and equipment. Due to their weight, the covers were extremely difficult to remove and replace safely, causing manual handling risks for operators. The equipment beneath the trench covers also posed a hazard to the public as the covers did not have a secure locking system. Inadequate security in the form of wooden fencing surrounding the perimeter further highlighted the need for modernization. modernisation.
In addition, the concrete covers had begun to break apart, potentially leading to a substantial risk to the underground valve and piping system. The obtrusive framework (pictured below) led to further difficulties and health and safety risks for engineers accessing equipment in the trench.
Fibrelite designed and manufactured bespoke super lightweight (A15 load rated) composite trench covers to offer easy access to the entire trench, improving efficiency and safety.
The new covers and frame allows for quick and easy access for people working onsite as the trench is no longer divided into separate sections. Fibrelite covers are corrosion-free, lightweight and durable, and can be safely removed and replaced by two people using the ergonomically designed FL7 lifting handle, preventing manual handling injuries by lifting from the waist. The provided trench covers were lockable for added security, preventing unauthorized unauthorised access.
The site now has a securable, aesthetically pleasing and maintenance-free access solution. Previous manual handling and safety concerns have been eliminated as onsite staff no longer put themselves in harm’s way by lifting heavy concrete covers and navigating around the hazardous framework which had previously been installed.
Author: